As CMA CGM acquired APL, the client needed to refurbish four (04) of their offices all over Pakistan in a very limited span of time. The challenge was not just to complete in a very short span of time but to maintain the same corporate quality of design and execution with other real challenges like wet monsoon season.
NUHA determined the corporate image of these four offices. We translated it into a 3D space design through logical planning stage and got approval from the client. Then made all offices at factory in Karachi, and shipped them to respective locations. All wet work, electrical work, HVAC, ducting etc. were done at four sites simultaneously as a parallel activity.
NUHA successfully executed all four offices as per CMA CGM global standard and provided high quality and cost-effective solutions within 45 working days.